Monday, 23 January 20126504, EBU-1, UC San DiegoLa Jolla, CA
| ||
| 12:30 | Coffee, Snacks, Socializing, and Laptop Connections | |
| 1:00 | Welcome, Meeting Logistics and Introductions | M. Tillack |
| 1:10 | Summary of Agenda | L. Waganer |
Project Plans and Progress | ||
| 1:15 | ARIES Project Update and Near-Term Objectives | F. Najmabadi |
ARIES Task Results (Engineering) | ||
| 1:30 | Updating the SCLL Design and ASC Documentation (pptx) | L. Carlson |
| 2:05 | Demonstration of 3-D Mockup of Divertor Design | L. Carlson |
| 2:15 | Break | |
| 2:30 | Progress on Liquid Metal Coolant Routing and MHD issues (ppt) | M. Tillack |
| 3:00 | Refinement of the Power Core Configuration of the ARIES-ACT (ppt) | X. Wang |
| 3:45 | Preliminary Stress Results of the Vacuum Vessel (pptx, pdf) | H. Hosseini |
| 4:05 | Fracture Analysis of Divertor Structures (pdf) | J. Blanchard |
| 4:35 | Recommended VV Design Load Criteria (Power Plant Relevant Design) (pdf) | J. Blanchard |
| 4:50 | Adjourn Meeting | |
Tuesday, 24 January 20126504, EBU-1, UC San DiegoLa Jolla, CA
| ||
| 8:00 | Coffee, Light Breakfast, Socializing, and Laptop Connections | |
| 8:25 | Summary of Today's Agenda | L. Waganer |
ARIES Task Results (Engineering) | ||
| 8:30 | Impact of a Water-Free VV on ARIES-ACT-SiC Inboard Radial Build (pdf) | L. El-Guebaly |
| 9:00 | Breakdown of Elements Degrading TBR of ARIES-ACT-SiC Blanket (pdf) | L. El-Guebaly |
| 9:30 | Nuclear Heating Profile for ARIES-ACT SiC Design (pdf) | L. El-Guebaly |
| 9:45 | Nuclear Heating Profile for ARIES-ACT DCLL Design (pdf) | L. El-Guebaly |
| 10:00 | Break | |
| 10:30 | Coolant Connections to the DCLL Blankets (pptx) | S. Malang |
ARIES Task Results (Physics) | ||
| 10:45 | MELCOR Model Development for ARIES-SA (ppt, pdf) | P. Humrickhouse |
| 11:15 | Update on Divertor Plasma Solutions (pdf) | M. Rensink |
| 11:45 | Lunch | |
| 1:00 | Progress on Physics for ARIES: ACT2 equilibria (ppt), disruptions (ppt), PFCheating (ppt), TSC (ppt) | C. Kessel |
| 1:45 | Progress on Optimization Results for Steady-State Plasma Solutions (pdf) | H. St. John |
| 2:30 | Break | |
Action Items and Future Plans | ||
| 2:45 | Action Item Review (xls) | F. Najmabadi |
| 3:15 | Next Call/Next Meeting/Discussion of future plans | F. Najmabadi |
| 3:45 | Adjourn Meeting | |