University of California, San Diego
Room 584, Engineering Building EBII
Wednesday, 1 December 1999 | ||
Administrative | ||
| 1:30 | Review of Agenda and Topics To Be Covered | Waganer |
| 1:40 | Status of DOE Fusion Program Priorities and Budgets | Dove |
| 2:00 | Summary of ARIES Program Plans, Holland Briefing, Status RS Papers | Najmabadi |
| 2:45 | Setting Next CC/E-Meeting and Dates for Project Meeting (w/ FIRE) | Najmabadi |
| 3:00 | Break | All |
ARIES-AT Physics | ||
| 3:15 | Report on Progress of Physics Group | Jardin |
| 3:45 | Physics Optimization of ARIES-AT | V. Chan, et al. |
| ARIES-RS Transport Modeling | Gary Staebler | |
| 4:15 | ARIES-AT: Extension of the Physics Basis for ARIES-RS | Kessel |
| 4:45 | Heating and Current Drive for ARIES-AT: An Update and Recommendations | Mau |
| 5:30 | Adjourn | Mau |
Thursday, 2 December 1999 | ||
Neutron Source Study | ||
| 8:30 | Status of Neutron Source Study | Steiner |
| 9:00 | Discussion of Metrics and Neutron Source Modeling | Miller |
| 9:30 | Update on Pu and Actinide Transmutation in Fusion Reactors | Cheng |
| 10:00 | Engineering and Nuclear Performance Data | Tillack |
| 10:15 | Break | |
Systems Studies | ||
| 10:30 | Systems and Economic Modeling of the ARIES-AT Design | R. Miller |
Safety Studies | ||
| 11:15 | Preliminary Analysis of Loss-of-Vacuum Events in ARIES-RS | D. Petti (Tillack) |
| 11:45 | Lunch | |
ARIES-AT Engineering | ||
| 1:00 | Summary of Nuclear Parameters, Radial Build, and Activation Analysis | El-Guebaly |
| 1:45 | Preliminary Design Definition and Integration of Power Core | Waganer |
| 2:15 | Initial Considerations on Core Configuration and Design Integration | Tillack |
| 2:45 | Status of ARIES-AT Blanket and First Wall Design | Raffray |
| 3:15 | Update on FW and Blanket Design | Sviatoslavsky |
| 3:45 | Break | |
| 4:00 | Innovative Blanket Design Approach | Malang |
| 4:30 | Divertor Options for ARIES-AT: Initial Considerations | Raffray |
| 5:00 | Status of TF and PF Magnet Design | Bromberg |
| 5:30 | Assessment of Tritium Handling and Storage Systems | Sze |
| 6:00 | Adjourn | |
|
Physics Subgroup Meeting (8:00-11:00)