Action Items
- Configuration and Maintenance
- Jan. 14:
Preliminary definition of integrated power core geometry and maintenance approach
- March 6:
Detailed definition of integrated power core geometry and maintenance approach (H&CD ports, vacuum ports, clearances, plumbing routing) - assess feasibility of providing inboard strike plate vacuum pumping.
- Heating and Current Drive
- March 9:
Select materials and define geometry/location/angle for machine integration and assessment
- PF and TF Magnets
- Dec. 10:
Obtain data from Bromberg including detail substantiation of magnet cost estimate plus magnet shape, cross-section, and required structure.
- Vacuum Vessel
- Jan. 14
Definition of integrated geometry
- Divertor
- Jan. 14:
Obtain from Petrie data on power flows to inboard and outboard regions
Drawings
- ARIES-AT Plan view
- ARIES-RS Plan view
- ARIES-AT Elevation view
- ARIES-RS Elevation view